During the construction the office will be open from Monday thru Friday from 9:00 am until 5:00 pm.

To our Kahlua family and friends:

Due to liability and safety issues, only the construction team and our own staff are allowed on the premises during the construction phase.

The Board of Directors has been contemplating a renovation project to the units of Kahlua Beach Club.  The work is anticipated to begin on June 2, 2018.​

All letters and updates will be posted on this page of the website.  

January 11, 2018 letter of Proposed Renovation Project from Board President

Frequently Asked Questions about the Renovation

March 7, 2018 update letter

April Renovation Project letter

Special Assessment Letter

May 1 note

Kahlua Unit Renovation Project Status Report - May 25, 2018

6/5/2018:  Note from Kahlua office staff - construction began Monday morning June 4 as scheduled.

Kahlua Unit Renovation Project Status Report 2 - June 22, 2018

6/27/18 - Reimbursement checks have been mailed with the exception of those owners who have not yet paid the special assessment fee.

Kahlua Unit Renovation Project Status Report - August 30, 2018

 

Week of June 4:Construction begins...

Photo section

Photos will be sent at various stages of the construction process.  Each group will be in a gallery.  To see an enlarged image, double click on the photo.  You may also click the arrows on each side to view each picture in the gallery.

Week of June 4

June 19

July 31

August 17

September 28

The following items still need to be installed: Drapes, Microwave, Handles for all cabinets, Shower door, Vanity Mirror, Medicine Cabinet and Closet area

"I love the new look!!! Thank you all for the hard work. I know it has not been easy.Great job by all!!!We appreciate you!!

Patti McLauchlin

November 24th - We're open!!  