Site/Building Updates

 

  • Landscaping in process – prep work

  • Plantings will go in starting today and finish on Monday

  • Molly (Town of FMB) is very happy with our work and prep on property site work.  “We’ve gone above and beyond expectations.”

  • New pavers order is in process

  • Not enough “old” pavers to complete lot.  Small area by maint. shed left open till new ones arrive

  • White pavers used for handicap spots with blue stripe

  • ADA & Stop signs for parking lot go in this Friday

  • May 7th hydrant install

  • Should allow us to apply for our Certificate of Occupancy shortly after hydrant install and final pending inspections

  • FMB Fire came to do a “courtesy” walk through.  No major issues.  Should make final inspection no issue

  • A couple exit signs test buttons not lighting up

  • 3 electrical boxes need covers

  • 3 Fire extinguishers to install

  • Need Southern Cross to spray fire & insecticide retardant on the Tiki’s, Life/Safety requirement

  • Need a couple turtle lights (3-4 week delivery).  Not an issue for inspections

  • Cat walk for pool equipment & fencing goes in Friday

  • A couple areas of pool pavers need adjustments

  • Pool ladders and railings need to be put in this week

  • Pool pumps are repaired and working

  • Pool chemical tanks are filled but not in service yet as they get adjusted.  Manually adding chemicals at this point

  • Dumpster has been removed from site

  • Parking lot was washed

  • Electrical panel in discussion with inspector and electrician – GFCI breaker discussion, code interpretation - scheduled for this Thursday

  • Small area of tile in breezeway needs to be “raised” to address water pooling by bathroom

  • Elevator door was adjusted to close smoothly

  • Elevator communications (emergency phone) is being addressed.  Signal strength is not at proper level

  • Pool heaters are on; a few more days for spa to “cure”