"A little bit of heaven on earth...."
April 29, 2026
Site/Building Updates
-
Landscaping in process – prep work
-
Plantings will go in starting today and finish on Monday
-
Molly (Town of FMB) is very happy with our work and prep on property site work. “We’ve gone above and beyond expectations.”
-
New pavers order is in process
-
Not enough “old” pavers to complete lot. Small area by maint. shed left open till new ones arrive
-
White pavers used for handicap spots with blue stripe
-
ADA & Stop signs for parking lot go in this Friday
-
May 7th hydrant install
-
Should allow us to apply for our Certificate of Occupancy shortly after hydrant install and final pending inspections
-
FMB Fire came to do a “courtesy” walk through. No major issues. Should make final inspection no issue
-
A couple exit signs test buttons not lighting up
-
3 electrical boxes need covers
-
3 Fire extinguishers to install
-
Need Southern Cross to spray fire & insecticide retardant on the Tiki’s, Life/Safety requirement
-
Need a couple turtle lights (3-4 week delivery). Not an issue for inspections
-
Cat walk for pool equipment & fencing goes in Friday
-
A couple areas of pool pavers need adjustments
-
Pool ladders and railings need to be put in this week
-
Pool pumps are repaired and working
-
Dumpster has been removed from site
-
Parking lot was washed
-
Electrical panel in discussion with inspector and electrician – GFCI breaker discussion, code interpretation - scheduled for this Thursday
-
Small area of tile in breezeway needs to be “raised” to address water pooling by bathroom
-
Elevator door was adjusted to close smoothly
-
Elevator communications (emergency phone) is being addressed. Signal strength is not at proper level
-
Pool heaters are on; a few more days for spa to “cure”