January 1, 2026

Site/Building Updates

 

Happy New Year's Eve To All - Here is an update from the last week. Have a good New Years...
 

  • Site is being cleared of excess sand

  • FDC trench should get backfilled

  • Received request from county for more info on FDC permit. Our Engineer is responding

  • Pool side is well graded for yard drain plans

  • Beachside “foot wash” pan being planned

  • Comcast coming out making some final adjustments on fiber first week of January

  • By weeks end, 95% of stucco work will be complete

  • Painting is underway, floors 3-5 done by weeks end, floors 1-2 by next weeks end

  • Painting on the “gulf side” should be done this week

  • Painting to continue around building

  • Gulf side scaffolding removed next week

  • Mini-split AC to be installed next week

  • Base rock to be placed for pavers install

  • Perimeter drains to be placed and installed

  • Tiki Huts scheduled week 2 of January

  • Pavers will then be installed after huts

  • Elevator in process – building cab is in process

  • Shower handles and doors have been corrected

  • Maintenance shed permit received, will be constructed once pool and equipment is “out of the way”