January 1, 2026
Site/Building Updates
Happy New Year's Eve To All - Here is an update from the last week. Have a good New Years...
-
Site is being cleared of excess sand
-
FDC trench should get backfilled
-
Received request from county for more info on FDC permit. Our Engineer is responding
-
Pool side is well graded for yard drain plans
-
Beachside “foot wash” pan being planned
-
Comcast coming out making some final adjustments on fiber first week of January
-
By weeks end, 95% of stucco work will be complete
-
Painting is underway, floors 3-5 done by weeks end, floors 1-2 by next weeks end
-
Painting on the “gulf side” should be done this week
-
Painting to continue around building
-
Gulf side scaffolding removed next week
-
Mini-split AC to be installed next week
-
Base rock to be placed for pavers install
-
Perimeter drains to be placed and installed
-
Tiki Huts scheduled week 2 of January
-
Pavers will then be installed after huts
-
Elevator in process – building cab is in process
-
Shower handles and doors have been corrected
-
Maintenance shed permit received, will be constructed once pool and equipment is “out of the way”