January 24, 2025

Site/Building Updates

  • The team from the Milestone Study was here this week along with EnviroStruct, Greg Jaster, LeAnn and John. They will be onsite again next week to go over in detail, a handful of items that need to be addressed as our construction continues

  • The stuccoing work has started, first with the power washing.  They will be working top to bottom

  • Florida Power & Light was out yesterday and has approved our new electrical power panel