Monday 3/3/25 meeting bullet points
-
Fire inspection will take place 3/6 on the first and second floor
-
Drywall should be delivered this week. Install should start next week (pending inspections)
-
Awaiting FDC (Fire Department) final drawing completion
-
We are putting a fire hydrant near the street
-
Estero will be partially closed for a bit to access the main water line
-
-
Contract for concrete repair will be finalized in the next couple of days and work may begin as soon as this week
-
This is the repair work for our Milestone study
-
Process will be closely reviewed and approved by Velocity (Milestone engineering firm) as things progress
-
No new permit will be needed as it will be done as repairs under existing contract/permits
-
-
LDO (Limited Development Order) permits could arrive in March which would be a big boost
-
This permit will arrive prior to the State of Florida permits providing full go ahead on the work site
-
-
A solid/sturdy ramp has been built outside the elevator to allow the demo of the old elevator and hopefully the install of the new one
-
Envirostruct working with elevator vendor on this process
-
-
The header/beam for the windows/door to the lobby should be complete in a couple of days
-
Leveling concrete was put in last week to level the lobby area flooring
-
All the new windows and doors will then be placed once they arrive on-site
-
-
No new time-line was offered. We probably will get a better understanding once all permits are received