Site/Building Updates
-
The inside of the building is pretty much complete
-
We installed the double interior doors in the office
-
We are installing the medicine cabinets in the nine units
-
Plan to install the windowsills next week. After that, we are for all intents and purposes substantially complete on the interiors
-
We have probably two more weeks of column repairs on the gulf side
-
We are shooting to start painting the building starting on December 15th
-
The pool grounding system has been completely installed and inspected by FMB
-
The spa has been repaired with respect to the plumbing, the new skimmer is installed, and it has been backfilled
-
Next up are the new coping and tile to match the pool
-
We are cleaning the project site and plan to bring our sitework contractor in to start the final grading
-
Needless to say, we feel we are starting to turn that corner on the project.