Site/Building Updates
-
New curbs are in and look good
-
Maintenance shed getting blocked up; good progress
-
South side privacy fence is now installed
-
New elevator doors are in on floors 2-5
-
John meeting with the landscaper soon
-
Tile floor on 5th is in process
-
Tub/tile grouted, caulking completed
-
Parking lot pavers going in. Should be completed next week (7-10 days)
-
Trash dumpster area to be configured and slab will be poured
-
It will take about 3 days to stucco seawall, ramp and the facing of the first floor step areas; painting after that
-
Tiki huts started Monday. Very fast progress, probably done this week
-
Elevator cab being assembled
-
Back splash on floors 1 and 2 completed this week
-
ROW still in process. Letter received but didn’t pertain to our project. Jim Ink connecting with county
-
Rooms on floors 3-5 should be 100% completed next week
-
Drapes and window coverings going in
-
Shuffleboard will be addressed this week