February 26, 2026

Site/Building Updates

 

  • New curbs are in and look good

  • Maintenance shed getting blocked up; good progress

  • South side privacy fence is now installed

  • New elevator doors are in on floors 2-5

  • John meeting with the landscaper soon

  • Tile floor on 5th is in process

  • Tub/tile grouted, caulking completed

  • Parking lot pavers going in.  Should be completed next week (7-10 days)

  • Trash dumpster area to be configured and slab will be poured

  • It will take about 3 days to stucco seawall, ramp and the facing of the first floor step areas; painting after that

  • Tiki huts started Monday.  Very fast progress, probably done this week

  • Elevator cab being assembled

  • Back splash on floors 1 and 2 completed this week

  • ROW still in process.  Letter received but didn’t pertain to our project. Jim Ink connecting with county

  • Rooms on floors 3-5 should be 100% completed next week

  • Drapes and window coverings going in

  • Shuffleboard will be addressed this week