

"A little bit of heaven on earth...."
February 28, 2026
Saturday Update:
We are closing in on completion
-
Tiki Huts are installed
-
Pavers in the drive up, driveway, and parking lot are at 50%
-
Finishing the pavers out front, making the few adjustments in back, and cutting in around the tiki hut posts will be completed next week
-
The maintenance building walls are up; the electrical infrastructure is in
-
The floor slab for shed and dumpster area slab will be poured next week
-
The exterior tile on 4th floor walkway is installed and the south stair tile is also installed
-
The waterproof membrane is in on 2nd walkway and the stair tile on north stair installed from 4 to 2
-
We expect all exterior tile to be complete next week
-
The elevator cab shell is installed, doors from 5 down to 2 are installed, and they should wrap up next week
-
We have two obstacles left to overcome: one in our control and the other is the ROW permit
-
Fountain Pools poured the equipment pad and we need a few details regarding the pump stands
-
They should start installing equipment on the pad, do the coping and tile at the spa, then prepare the pool for pebbling
-
Their (pool company) schedule suggests they will be requesting final FMB inspections on 3/10 & 11. Then we do State Health
-
Right now the interior spaces are slated for Final cleaning 2 thru 5 either March 6th or the 9th, as punch list is close
-
We are petitioning Jennifer (FMB Fire) to allow KBC to start staging and stocking the units on 1 and 2 before the C of O
-
Once we get ROW, a few days will be needed to get company on-site and install hydrant. We can then discuss details of opening date



