February 6, 2026

Site/Building Updates

 

  • Even with yesterday’s rain out we are still making significant progress​

  • Pavers are 75% compete in back

  • They will be finishing pavers at the grill side of the building by mid-next week

  • The pool collection tanks have been positioned and the walls have been poured

  • Tank forms are being stripped today

  • Railings on the first floor will be complete today

  • Tile contractor will start on the first-floor patios and breezeway

  • Stone counters in the office and kitchen are on-site and will also be installed today

  • Heading into next week we plan to have our last two building final inspections completed for HVAC and plumbing

  • Toward the end of the week we plan to pour the concrete curbs out front so that paver work can continue out there

  • Expecting the underground pool plumbing to be completed so that we can lay out the maintenance building

  • Hope to have the fencing contractor out next week to start

  • We expect the elevator contractor to come out and get started on the cab… Fingers crossed!