Even with yesterday’s rain out we are still making significant progress
-
Pavers are 75% compete in back
-
They will be finishing pavers at the grill side of the building by mid-next week
-
The pool collection tanks have been positioned and the walls have been poured
-
Tank forms are being stripped today
-
Railings on the first floor will be complete today
-
Tile contractor will start on the first-floor patios and breezeway
-
Stone counters in the office and kitchen are on-site and will also be installed today
-
Heading into next week we plan to have our last two building final inspections completed for HVAC and plumbing
-
Toward the end of the week we plan to pour the concrete curbs out front so that paver work can continue out there
-
Expecting the underground pool plumbing to be completed so that we can lay out the maintenance building
-
Hope to have the fencing contractor out next week to start
-
We expect the elevator contractor to come out and get started on the cab… Fingers crossed!