

"A little bit of heaven on earth...."
January 24, 2026
Site/Building Updates
Another busy week!
-
Inside we are working on punch list
-
Finished the floor tile in the bathroom in unit 201
-
Started balcony tile on 2nd floor
-
Outside we have finished the yard drains in back and on the south side
-
Placed the base rock and compacted it
-
We are now at the "finished elevation" before sand and pavers
-
On Saturday we are pouring new caps on the sea wall and the two walls at the ramp down to the beach. This is a field condition that was necessitated by the pool coping elevation established by the Civil Engineer
-
The shuffleboard court base pad is being formed today and pouring the concrete on Monday
-
The exterior painting is moving along; they are finished painting the second-floor walkway and stair towers today
-
The electrician is trimming behind the painter and setting the conduit for the power in the two large tiki huts
-
Next week:
-
The collector tanks for the pool are coming on Monday and will be plumbed. After that, we pour the walls around the tanks and backfill everything
-
Also, the pool pavers and necessary sand start on Monday
-
Elevator tower exterior will be painted off the lift and we expect the balcony tile to be completed on 2nd floor
-
From there we will hopefully start the perimeter fencing provided FMB issues the permit
-
Expecting elevator week 3 of February
-
Still no update from Lee County on the LDO
-
No new open date at this point



