Site/Building Updates
-
All pool furniture has now been delivered, and pool has been pebbled.
-
Filling the pool this weekend will cure the pebbling, which needs to sit for several days before starting up the pool equipment.
-
Poolside showers have been received and will be installed next week.
-
We are still waiting on the hydrant permit. Our Engineer has been unavailable due to health reasons but on Monday will address a question that Lee County has. We cannot reopen without the hydrant being installed, and we cannot schedule the hydrant install until we receive the ROW permit. We do not have a reopening date.
-
We have asked the FMB Fire Department if we can start furnishing and setting up the office but have not yet heard back.
-
Wendy and I continue to work from home the majority of the time, with trips to Kahlua for meetings and to pick up mail, and John and Craig continue to work on all the details that will pull Kahlua together.
Envirostruct will send their update tomorrow.