October 21,  2025

Site/Building Updates

Here is a summary of today’s meeting: Looking forward to our call Thursday morning.

 

  • Pool “matting” on pool sides is now in place

  • Pool stairs structure should be done today

  • Bonding clamps being put on helical pilings this week

  • Pool concrete should be “shot” sprayed later this week or next week

  • Final electrical being done and completed on 1 & 2 this week

  • Tiles and grouting on 1 & 2 will be done by Wednesday

  • Awaiting office door to be installed

  • Work on north stairs continues

  • Manit. shed revisions will be done in the next couple days

  • Lee County has ROW request in house

  • Opening schedule has not changed as of today – January 2026

  • Elevator piston should be installed 1st week of November

  • Everyone in the process is fully aware of final inspections needing to be scheduled so potential delays are kept minimal

  • Crew will work from pool to spa area with new plumbing

  • Once in that area, spa can be uncovered to see its condition

  • Paving company is ready to install pool pavers once it’s prepped

  • Tiki Hut supplier (Southern Cross) also “standing by” for install

  • LeAnn provided interior office/lobby/kitchen colors

  • Exterior paint choices will be provided by KBC late this week – White exterior with a blue (shade TBD) trim