"A little bit of heaven on earth...."
October 21, 2025
Site/Building Updates
Here is a summary of today’s meeting: Looking forward to our call Thursday morning.
-
Pool “matting” on pool sides is now in place
-
Pool stairs structure should be done today
-
Bonding clamps being put on helical pilings this week
-
Pool concrete should be “shot” sprayed later this week or next week
-
Final electrical being done and completed on 1 & 2 this week
-
Tiles and grouting on 1 & 2 will be done by Wednesday
-
Awaiting office door to be installed
-
Work on north stairs continues
-
Manit. shed revisions will be done in the next couple days
-
Lee County has ROW request in house
-
Opening schedule has not changed as of today – January 2026
-
Elevator piston should be installed 1st week of November
-
Everyone in the process is fully aware of final inspections needing to be scheduled so potential delays are kept minimal
-
Crew will work from pool to spa area with new plumbing
-
Once in that area, spa can be uncovered to see its condition
-
Paving company is ready to install pool pavers once it’s prepped
-
Tiki Hut supplier (Southern Cross) also “standing by” for install
-
LeAnn provided interior office/lobby/kitchen colors
-
Exterior paint choices will be provided by KBC late this week – White exterior with a blue (shade TBD) trim