Site/Building Updates
Some information from our construction meeting this week.
-
Helical pool pilings are hopefully scheduled for this week. Extensions are required to get to a “solid base” which is up to 19 feet below grade on some pilings
-
Once pilings are set, about 3 weeks more to complete pool itself
-
Once pool is done, it will be backfilled and graded
-
Scaffolding can then go up to finish gulf-side column repairs
-
Then final stucco can be done on building exterior
-
South stairwell concrete work is now done
-
North stairwell is being worked on this week
-
Elevator: piston still needs to be replaced and schedule is in process. The elevator company, TKD communications, is a bit difficult
-
Looking at door hardware needs and possible door replacement on 2-5 (this is in process)
-
FDC - Fire Hydrant – “right of way” permit still in process. Engineer, to get info moving
-
Getting quotes on exterior hallway flooring on floors 2 and 4
-
Slider adjustments should be underway this week
-
Maintenance shed permit needed minor changes with regard to its electrical panel. Will submit change to town this week
-
Shed must have “break-away” walls and requires electrical panel. Will be relocated
-
Bath barn door track being assembled this week to test strength
-
New barn doors should arrive by end of October
-
Looking at adding a small drop ceiling outside office to cover utilities to electrical room which will make it look nicer
-
Soft goods and furniture should be able to be placed in units mid December
At this point, no new adjustments have been made to the completion date of January 2026