October 8,  2025

Site/Building Updates

 

Some information from our construction meeting this week.​
 

  • Helical pool pilings are hopefully scheduled for this week.  Extensions are required to get to a “solid base” which is up to 19 feet below grade on some pilings

  • Once pilings are set, about 3 weeks more to complete pool itself

  • Once pool is done, it will be backfilled and graded

  • Scaffolding can then go up to finish gulf-side column repairs

  • Then final stucco can be done on building exterior

  • South stairwell concrete work is now done

  • North stairwell is being worked on this week

  • Elevator: piston still needs to be replaced and schedule is in process.  The elevator company, TKD communications, is a bit difficult

  • Looking at door hardware needs and possible door replacement on 2-5 (this is in process)

  • FDC - Fire Hydrant – “right of way” permit still in process. Engineer, to get info moving

  • Getting quotes on exterior hallway flooring on floors 2 and 4

  • Slider adjustments should be underway this week

  • Maintenance shed permit needed minor changes with regard to its electrical panel.  Will submit change to town this week

  • Shed must have “break-away” walls and requires electrical panel.  Will be relocated

  • Bath barn door track being assembled this week to test strength

  • New barn doors should arrive by end of October 

  • Looking at adding a small drop ceiling outside office to cover utilities to electrical room which will make it look nicer

  • Soft goods and furniture should be able to be placed in units mid December

    At this point, no new adjustments have been made to the completion date of January 2026